Supreme Court

Following the signature of an MOU in November 2016 between the Government of Mauritius and the Government of India, a grant assistance of USD 30M has been provided by the latter for the project of a New Supreme Court.
The Government of India has appointed NBCC (India) Ltd as the Project Management Consultant (PMC). The Government of Mauritius on its part has appointed Landscope (Mauritius) Ltd as the Implementing Agency to advise the Client (Supreme Court of Mauritius) on each and every aspect of the project and to safeguard the interests of the Client.
The Supreme Court Building covers a floor area of 25,000 sqm on 12 floors, including basement. Tenders for construction works have been launched in India.
The concept drawings and Bid Documents have been finalized with the PMC.
The following milestones have now been established:
1. Invitation To Tender 19 September 2017
2. Opening of Bids 17 October 2017
3. Award of Tender 31 October 2017
4. Start of Work (Estimated) 30 November 2017
5. Completion of Project 30 November 2019